Before you accept a new building at handover, check that the completed work matches the agreed drawings and specifications, the services work correctly, and you have the required approvals and records. Inspect the building with suitably qualified professionals, record every defect, and agree in writing which items the contractor must correct before you accept possession.
What documents do you need at handover?
Ask for the handover pack before your inspection so you can compare the completed building with the agreed requirements. Don't assume that a neat finish means concealed work, installed equipment or design changes meet the specification.
Check that you receive the following documents, where applicable:
- Approved architectural, structural and building services drawings, together with authorised design changes.
- As-built drawings showing what the contractor actually installed, including concealed pipework, cables, valves and drainage routes.
- Completion or occupancy approvals required by the relevant authority, with any outstanding conditions clearly listed.
- Electrical, plumbing, waterproofing and other inspection or test records required by the project specification.
- Operating manuals, maintenance schedules, equipment warranties and supplier contact details.
- A list of keys, access cards, meter references and equipment identification numbers.
Check that certificates identify the correct building, installation and test date. Confirm that the as-built drawings reflect significant changes made during construction rather than simply reproducing the original design.
How to inspect the completed building
Walk through every room and mark your findings on a floor plan, then inspect the roof, accessible service spaces and external works. Ask an independent building inspector or suitably qualified construction professional to help you identify defects you might miss during a casual visit.
Look for cracks, damp patches, staining, loose finishes and signs of movement. Ask a structural engineer to assess unexplained cracks, noticeable deflection or distorted structural elements; you can't judge whether a defect is harmless from crack width alone.
Check walls, ceilings, tiles and flooring against the agreed finish and workmanship requirements. Look for uneven surfaces, chipped edges, open joints and changes in level that create trip hazards. Ask for further investigation if floor tiles sound hollow, rather than assuming every hollow sound proves failure.
Open and close each door and window. Check alignment, locks, seals, glazing and hardware, and confirm that doors don't scrape the floor. Check that fitted cupboards, worktops, sanitary fittings and accessories are securely fixed and undamaged.
Outside, check paving slopes, boundary works, inspection chamber covers and drainage channels. Have a competent person inspect roof waterproofing details, outlets, flashings and protective finishes without damaging them or approaching unprotected edges.
How to test building services before handover
Operate every tap, shower and flushing cistern, and check visible joints for leaks. Run several outlets together to identify obvious pressure problems, then watch how sinks, showers and floor drains empty. Ask for an investigation if you find slow drainage, leaks, persistent odours or water collecting away from an outlet.
Request the specified pressure-test and drainage-test records. For bathrooms, roofs and other waterproofed areas, ask for evidence that the contractor completed testing before covering the waterproofing with finishes. If you arrange a further flood test, make sure the contractor follows an approved procedure that controls loading and prevents water damage.
Have a qualified electrician inspect the installation and explain its test results. You can't verify earthing, insulation resistance or protective-device operation simply by switching on lights. Keep distribution board covers closed and leave live electrical testing to the electrician.
Check socket and switch locations against the drawings, check that circuit labels identify the correct circuits, and make sure you can reach isolation switches. Ask the electrician to demonstrate the residual current devices, where fitted, and explain how you should test them after you move in.
For ventilation, air conditioning, pumps, water heating, lifts and backup power, request commissioning records and arrange to witness demonstrations. The Whole Building Design Guide describes commissioning as a process for verifying and documenting that building systems meet the owner's requirements, not merely confirming that equipment starts.
What safety checks should you make?
With the responsible specialist, check the completed fire safety measures against the approved design and applicable requirements. The required measures depend on the building's use, height, layout and occupancy, so don't rely on a generic checklist instead of that review.
Where provided, inspect escape routes, exit signs, emergency lighting, alarms, extinguishers, fire doors and firefighting systems. Confirm that escape doors work as intended and that stored materials, locked gates or unfinished work don't obstruct exits.
Ask for fire system test records and a demonstration by the responsible contractor. Check that fire doors have compatible, working components, including closers and latches where specified; the National Fire Protection Association publishes standards covering fire doors and other fire protection systems.
Check stairs, handrails, guards and accessible routes against the approved details. Confirm that security controls don't prevent emergency escape, and that maintenance staff can safely reach equipment that needs routine inspection.
How to record building defects
Prepare a written snagging list, a record of incomplete, damaged or defective work. Give each item a unique reference, exact location, photograph, description and required action. List safety concerns and failed systems separately from cosmetic defects.
For each item, record who will correct it, the agreed completion date and how you'll verify the repair. Avoid vague entries such as “plumbing incomplete”; identify the leaking joint, affected room or missing test record.
Arrange a follow-up inspection before marking items as complete. Check the repaired work and adjacent finishes, and repeat relevant tests where repairs could affect performance. Don't mark a defect as corrected solely because someone reports that the work is finished.
What should you check before signing?
Read the handover certificate alongside your contract. Confirm what signing means for possession, insurance responsibilities, outstanding work, warranty start dates and the defects notification period. Don't assume these dates are identical.
Attach an agreed list of outstanding items and keep signed copies of the handover records. Ask a lawyer or contract administrator to clarify any wording that appears to waive your rights or accept disputed work.
Before releasing a final payment, check the contractual payment conditions and obtain the relevant professional certification. Follow the contract and applicable law if you retain or withhold money. Collect the remaining keys, manuals and access credentials, and ask for practical training on shut-off valves, electrical isolation and emergency procedures before you take control.